ITAC Assessment: OR0127
ITAC logo
ITAC Assessment: OR0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product FROZEN FRUIT
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 6,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,590 885,991
kWh
Natural Gas $1,248 238
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,392 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,392

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $117 - $117
2,931
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $23 - $23
586
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $287 - $272
4,103
kWh
$15
04 2.3212: Optimize plant power factor $400 $1,125 $400
-
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $521 - $108
2,931
kWh
$413
06 2.4133: Use most efficient type of electric motors $44 $201 $44
586
kWh
-
TOTAL RECOMMENDED $1,392 $1,326 $964
11,137
kWh
$428
TOTAL IMPLEMENTED $1,392 $1,326 $964
11,137
kWh
$428
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs