ITAC Assessment: OR0125
ITAC logo
ITAC Assessment: OR0125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product MALTED BARLEY
NAICS
n/a
SIC 2083: Malt
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area
n/a
Annual Production 11,800,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $835,617 33,943,435
kWh
Natural Gas $72,536 20,581
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,199 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $61,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $18,739 - $8,304
422,626
kWh
$10,435
02 2.4133: Use most efficient type of electric motors $2,392 $6,072 $2,392
90,270
kWh
-
03 2.4322: Use or replace with energy efficient substitutes $12,391 $35,042 $12,391
483,001
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $6,743 - $3,798
155,920
kWh
$2,945
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,934 $83,040 $20,934
1,065,064
kWh
-
TOTAL RECOMMENDED $61,199 $124,154 $47,819
2,216,881
kWh
$13,380
TOTAL IMPLEMENTED $61,199 $124,154 $47,819
2,216,881
kWh
$13,380
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs