ITAC Assessment: OR0122
ITAC logo
ITAC Assessment: OR0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product ICE CREAM, FROZEN YOGURT
NAICS
n/a
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area
n/a
Annual Production 3,000
Tgal
Production Hrs. Annual 2,625
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,867 2,952,521
kWh
Natural Gas $25,656 6,499
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,191 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,191

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6231: Utilize controls to operate equipment only when needed $1,529 - - $1,147
-
MMBtu
$382
02 2.3212: Optimize plant power factor $1,640 $1,700 $1,640
-
kWh
- -
03 2.7111: Reduce illumination to minimum necessary levels $76 $60 $76
2,052
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,626 - $2,310
68,581
kWh
- $1,316
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $378 $400 $378
12,603
kWh
- -
06 2.2136: Install / repair insulation on steam lines $361 $596 - $361
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $77 $37 $77
2,345
kWh
- -
08 2.1232: Keep boiler tubes clean $354 - - $354
-
MMBtu
-
09 2.4133: Use most efficient type of electric motors $150 $462 $150
4,982
kWh
- -
TOTAL RECOMMENDED $8,191 $3,255 $4,631
90,563
kWh
$1,862
-
MMBtu
$1,698
TOTAL IMPLEMENTED $8,191 $3,255 $4,631
90,563
kWh
$1,862
-
MMBtu
$1,698
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs