ITAC Assessment: OR0102
ITAC logo
ITAC Assessment: OR0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product DOOR FRAMES
NAICS
n/a
SIC 2431: Millwork
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area
n/a
Annual Production 5,000
thousand feet
Production Hrs. Annual 4,510
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,031 2,420,574
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,311 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $925

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.3212: Optimize plant power factor $925 $1,950 $925
-
kWh
02 2.4133: Use most efficient type of electric motors $257 $595 $257
6,448
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,129 $6,255 $2,129
52,169
kWh
TOTAL RECOMMENDED $3,311 $8,800 $3,311
58,617
kWh
TOTAL IMPLEMENTED $925 $1,950 $925
-
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs