ITAC Assessment: OR0083
ITAC logo
ITAC Assessment: OR0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product DIMENSIONED LUMBER
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 71
Plant Area
n/a
Annual Production 45,000
thousand feet
Production Hrs. Annual 6,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,230 5,021,981
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,569 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,496

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $1,850 - $1,850
38,101
kWh
02 2.3212: Optimize plant power factor $20,444 $16,800 $20,444
-
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,646 $5,000 $3,646
140,094
kWh
04 2.8114: Change rate schedules or other changes in utility service $24,439 $46,216 $24,439
-
kWh
05 2.4133: Use most efficient type of electric motors $190 $490 $190
5,275
kWh
TOTAL RECOMMENDED $50,569 $68,506 $50,569
183,470
kWh
TOTAL IMPLEMENTED $5,496 $5,000 $5,496
178,195
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs