| Assessment Year | 1990 |
|---|---|
| Principal Product | MARASCHINO CHERRIES |
| NAICS |
n/a
|
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
n/a
|
| Annual Production | 11,000,000
lb
|
| Production Hrs. Annual | 3,400
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $98,529 | 1,966,882 |
kWh
|
$0.050 |
| Natural Gas | $143,908 | 40,310 |
MMBtu
|
$3.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,522 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,080 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2163: Use minimum steam operating pressure | $1,772 | - | - |
$1,772
-
MMBtu
|
|
| 02 | 2.2123: Insulate feedwater tank | $755 | $297 | - |
$755
-
MMBtu
|
|
| 03 | 2.2136: Install / repair insulation on steam lines | $658 | $478 | - |
$658
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,589 | - |
$1,589
19,343
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $191 | $166 |
$191
3,810
kWh
|
- | |
| 06 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $3,471 | $3,766 | - |
$3,471
-
MMBtu
|
|
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $491 | $500 | - |
$491
-
MMBtu
|
|
| 08 | 2.4239: Eliminate or reduce compressed air usage | $2,807 | $6,145 |
$2,807
55,979
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $788 | $2,117 |
$788
9,086
kWh
|
- | |
| TOTAL RECOMMENDED | $12,522 | $13,469 |
$5,375
88,218
kWh
|
$7,147
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,080 | $500 |
$1,589
19,343
kWh
|
$491
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs