| Assessment Year | 1989 |
|---|---|
| Principal Product | BUSINESS FORMS |
| NAICS |
n/a
|
| SIC | 2761: Manifold Business Forms |
| Sales Range | $5 M to 10M |
| # of Employees | 87 |
| Plant Area |
n/a
|
| Annual Production | 251
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $40,677 | 941,970 |
kWh
|
$0.043 |
| Fuel Oil #6 | $3,226 | 623 |
MMBtu
|
$5.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,136 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,064 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $794 | $500 |
$794
18,464
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $147 | $117 |
$121
2,931
kWh
|
- | $26 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $228 | $213 |
$254
5,862
kWh
|
- | $(-26.0) | |
| 04 | 2.4133: Use most efficient type of electric motors | $78 | $94 |
$78
1,758
kWh
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $925 | $1,340 | - |
$925
-
MMBtu
|
- | |
| 06 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $833 | $1,175 |
$365
10,844
kWh
|
$468
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $131 | $244 |
$153
3,517
kWh
|
- | $(-22.0) | |
| TOTAL RECOMMENDED | $3,136 | $3,683 |
$1,765
43,376
kWh
|
$1,393
-
MMBtu
|
$(-22.0) | ||
| TOTAL IMPLEMENTED | $2,064 | $2,226 |
$1,644
40,445
kWh
|
$468
-
MMBtu
|
$(-48.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs