ITAC Assessment: OR0057
ITAC logo
ITAC Assessment: OR0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product RESINS
NAICS
n/a
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area
n/a
Annual Production 358,000
lb
Production Hrs. Annual 8,640
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $252,809 10,257,913
kWh
Natural Gas $256,703 67,429
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,340 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,990

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2121: Increase amount of condensate returned $2,420 $870 - $2,252
-
MMBtu
$168
02 2.2122: Install / repair insulation on condensate lines $201 $145 - $201
-
MMBtu
-
03 2.3212: Optimize plant power factor $6,061 $5,850 $6,061
-
kWh
- -
04 2.4133: Use most efficient type of electric motors $308 $389 $308
12,309
kWh
- -
05 2.2444: Use hot process fluids to preheat incoming process fluids $1,219 $1,903 - $1,010
-
MMBtu
$209
06 2.2444: Use hot process fluids to preheat incoming process fluids $6,972 $28,690 - $6,972
-
MMBtu
-
07 2.2449: Recover heat from exhausted steam, hot air or hot water $2,159 $6,871 $(-484.0)
(-19,343)
kWh
$2,643
-
MMBtu
-
TOTAL RECOMMENDED $19,340 $44,718 $5,885
(-7,034)
kWh
$13,078
-
MMBtu
$377
TOTAL IMPLEMENTED $8,990 $7,254 $6,369
12,309
kWh
$2,453
-
MMBtu
$168
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs