| Assessment Year | 1989 |
|---|---|
| Principal Product | RESINS |
| NAICS |
n/a
|
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $10 M to 50M |
| # of Employees | 66 |
| Plant Area |
n/a
|
| Annual Production | 358,000
lb
|
| Production Hrs. Annual | 8,640
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $252,809 | 10,257,913 |
kWh
|
$0.025 |
| Natural Gas | $256,703 | 67,429 |
MMBtu
|
$3.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,340 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,990 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2121: Increase amount of condensate returned | $2,420 | $870 | - |
$2,252
-
MMBtu
|
$168 | |
| 02 | 2.2122: Install / repair insulation on condensate lines | $201 | $145 | - |
$201
-
MMBtu
|
- | |
| 03 | 2.3212: Optimize plant power factor | $6,061 | $5,850 |
$6,061
-
kWh
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $308 | $389 |
$308
12,309
kWh
|
- | - | |
| 05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $1,219 | $1,903 | - |
$1,010
-
MMBtu
|
$209 | |
| 06 | 2.2444: Use hot process fluids to preheat incoming process fluids | $6,972 | $28,690 | - |
$6,972
-
MMBtu
|
- | |
| 07 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $2,159 | $6,871 |
$(-484.0)
(-19,343)
kWh
|
$2,643
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $19,340 | $44,718 |
$5,885
(-7,034)
kWh
|
$13,078
-
MMBtu
|
$377 | ||
| TOTAL IMPLEMENTED | $8,990 | $7,254 |
$6,369
12,309
kWh
|
$2,453
-
MMBtu
|
$168 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs