Assessment Year | 1988 |
---|---|
Principal Product | POTATO FLAKES & STARCH |
NAICS |
n/a
|
SIC | 2034: Dried and Dehydrated Fruits, Vegetables, and Soup Mixes |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 24,000,000
lb
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $182,468 | 2,920,574 |
kWh
|
$0.062 |
LPG | $210,439 | 53,626 |
MMBtu
|
$3.92 |
Fuel Oil #4 | $118,728 | 47,382 |
MMBtu
|
$2.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,712 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,045 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #4 Savings |
---|---|---|---|---|---|---|---|
01 | 2.2163: Use minimum steam operating pressure | $506 | - | - |
$324
-
MMBtu
|
$182
-
MMBtu
|
|
02 | 2.4133: Use most efficient type of electric motors | $471 | $258 |
$471
7,620
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $1,171 | $627 | - |
$749
-
MMBtu
|
$422
-
MMBtu
|
|
04 | 2.2136: Install / repair insulation on steam lines | $1,477 | $1,900 | - |
$947
-
MMBtu
|
$530
-
MMBtu
|
|
05 | 2.2122: Install / repair insulation on condensate lines | $433 | $908 | - |
$277
-
MMBtu
|
$156
-
MMBtu
|
|
06 | 2.3212: Optimize plant power factor | $2,458 | $5,400 |
$2,458
-
kWh
|
- | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $5,196 | $12,635 | - |
$3,324
-
MMBtu
|
$1,872
-
MMBtu
|
|
TOTAL RECOMMENDED | $11,712 | $21,728 |
$2,929
7,620
kWh
|
$5,621
-
MMBtu
|
$3,162
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,045 | $8,835 |
$2,458
-
kWh
|
$2,297
-
MMBtu
|
$1,290
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Fuel Oil #4 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs