| Assessment Year | 1987 |
|---|---|
| Principal Product | FRUIT CONCENTRATE |
| NAICS |
n/a
|
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
n/a
|
| Annual Production | 59,400,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $194,013 | 3,575,029 |
kWh
|
$0.054 |
| Natural Gas | $288,161 | 65,940 |
MMBtu
|
$4.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,177 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,631 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $922 | - |
$922
17,292
kWh
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $389 | $96 | - |
$389
-
MMBtu
|
- | |
| 03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,474 | - |
$1,474
27,257
kWh
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $3,519 | $1,536 | - |
$3,519
-
MMBtu
|
- | |
| 05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,969 | $3,600 |
$4,969
92,028
kWh
|
- | - | |
| 06 | 2.2422: Use waste heat from hot flue gases to generate steam | $4,103 | $3,000 | - |
$4,103
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,024 | $1,092 |
$1,142
21,102
kWh
|
- | $(-118.0) | |
| 08 | 2.4133: Use most efficient type of electric motors | $777 | $746 |
$777
14,361
kWh
|
- | - | |
| TOTAL RECOMMENDED | $17,177 | $10,070 |
$9,284
172,040
kWh
|
$8,011
-
MMBtu
|
$(-118.0) | ||
| TOTAL IMPLEMENTED | $6,631 | $3,470 |
$2,841
52,755
kWh
|
$3,908
-
MMBtu
|
$(-118.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs