| Assessment Year | 2001 |
|---|---|
| Principal Product | sewer cleaning equipment |
| NAICS |
n/a
|
| SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
24,000
ft2
|
| Annual Production | 15,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $12,342 | 126,792 |
kWh
|
$0.097 |
| Electricity Demand | $2,167 | 800 |
kW-mo/yr
|
$2.71 |
| Electricity Fees | $2,030 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $159,673 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,934 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8112: Combine utility meters | $3,197 | $7,500 | - | - | - | - | $3,197 | - | |
| 02 | 2.7144: Install spectral reflectors / delamp | $1,249 | $2,745 |
$1,062
10,616
kWh
|
$187
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $934 | $130 |
$1,100
11,001
kWh
|
$194
-
kW-mo/yr
|
- | $(-360.0) | - | - | |
| 04 | 3.3121: Use screening, magnetic separation to remove contaminants | $2,293 | $40 | - | - |
$2,293
-
gal
|
- | - | - | |
| 05 | 4.521: Clear and rent existing space | $121,000 | $12,000 | - | - | - | - | $121,000 | - | |
| 06 | 4.611: Begin a practice of predictive / preventative maintenance | $18,500 | $600 | - | - | - | $(-2,400.0) | - | $20,900 | |
| 07 | 4.321: Optimize production lot sizes and inventories | $12,500 | - | - | - | - | - | $12,500 | - | |
| TOTAL RECOMMENDED | $159,673 | $23,015 |
$2,162
21,617
kWh
|
$381
-
kW-mo/yr
|
$2,293
-
gal
|
$(-2,760.0) | $136,697 | $20,900 | ||
| TOTAL IMPLEMENTED | $31,934 | $730 |
$1,100
11,001
kWh
|
$194
-
kW-mo/yr
|
- | $(-2,760.0) | $12,500 | $20,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs