Assessment Year | 1987 |
---|---|
Principal Product | WALL PANELING & PLYWOOD |
NAICS |
n/a
|
SIC | 2436: Softwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
n/a
|
Annual Production | 12,800,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $538,373 | 13,662,075 |
kWh
|
$0.039 |
Natural Gas | $281,160 | 49,905 |
MMBtu
|
$5.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,820 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,085 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2163: Use minimum steam operating pressure | $1,499 | - | - |
$1,499
-
MMBtu
|
- | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $581 | - |
$581
14,654
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,003 | - |
$4,003
99,941
kWh
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,654 | $300 | - |
$3,654
-
MMBtu
|
- | |
05 | 2.7231: Use radiant heater for spot heating | $1,964 | $1,740 |
$1,964
48,945
kWh
|
- | - | |
06 | 2.3212: Optimize plant power factor | $3,642 | $3,325 |
$3,642
-
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $1,190 | $1,201 |
$1,190
29,894
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,287 | $900 |
$2,240
55,979
kWh
|
- | $47 | |
TOTAL RECOMMENDED | $18,820 | $7,466 |
$13,620
249,413
kWh
|
$5,153
-
MMBtu
|
$47 | ||
TOTAL IMPLEMENTED | $15,085 | $4,525 |
$9,885
155,920
kWh
|
$5,153
-
MMBtu
|
$47 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs