ITAC Assessment: OK1170
ITAC logo
ITAC Assessment: OK1170
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product plastic bottles
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 146,000
ft2
Annual Production 120,000,000
units
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $438,828 9,629,200
kWh
Electricity Demand $297,064 41,323
kW-mo/yr
Natural Gas $6,222 803
MMBtu
Waste Disposal Costs
Water Usage $26,810 3,423
Tgal
Water Disposal $17,038 2,401
Tgal
TOTAL YEARLY COSTS $785,962
RECOMMENDED SAVINGS* $144,634 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $51,051 $772,200 $51,051
1,109,809
kWh
- -
02 2.7232: Replace existing hvac unit with high efficiency model $3,425 $7,920 $3,425
74,456
kWh
- -
03 2.7226: Use computer programs to optimize hvac performance $17,696 $126,000 $17,696
384,685
kWh
- -
04 2.7211: Clean and maintain refrigerant condensers and towers $20,345 $2,465 $20,345
442,276
kWh
- -
05 2.3212: Optimize plant power factor $10,143 $29,160 - - $10,143
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $26,153 $68,845 $26,153
568,545
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $4,808 $2,460 $3,958
86,050
kWh
$850
-
kW-mo/yr
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $6,745 - $6,745
146,634
kWh
- -
09 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,268 - - $4,268
-
kW-mo/yr
-
TOTAL RECOMMENDED $144,634 $1,009,050 $129,373
2,812,455
kWh
$5,118
-
kW-mo/yr
$10,143
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs