| Assessment Year | 2026 |
|---|---|
| Principal Product | Roofing products for commercial buildings |
| NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
| SIC | 2952: Asphalt Felts and Coatings |
| Sales Range | $10 M to 50M |
| # of Employees | 20 |
| Plant Area |
500,000
ft2
|
| Annual Production | 10,000
ton
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $693,000 | 12,600,000 |
kWh
|
$0.055 | |
| Electricity Demand | $966,960 | 72,000 |
kW-mo/yr
|
$13.43 | |
| Natural Gas | $72,450 | 11,303 |
MMBtu
|
$6.41 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,422 | 147 |
Tgal
|
$9.67 | |
| Water Disposal | $584 | 147 |
Tgal
|
$3.97 | |
| TOTAL YEARLY COSTS | $1,734,416 | ||||
| RECOMMENDED SAVINGS* | $204,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $201,784 | $2,044,800 |
$201,784
3,668,794
kWh
|
|
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $1,105 | $3,355 |
$1,105
20,096
kWh
|
|
| 03 | 2.7211: Clean and maintain refrigerant condensers and towers | $566 | $780 |
$566
10,287
kWh
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $966 | $1,847 |
$966
17,563
kWh
|
|
| TOTAL RECOMMENDED | $204,421 | $2,050,782 |
$204,421
3,716,740
kWh
|
||
| TOTAL IMPLEMENTED | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs