| Assessment Year | 2025 |
|---|---|
| Principal Product | Casino recreation |
| NAICS | 713210: Casinos (except Casino Hotels) |
| SIC | 7999: Amusement and Recreation Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 76 |
| Plant Area |
9,500
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $115,344 | 1,647,777 |
kWh
|
$0.070 | |
| Natural Gas | $3,150 | 583 |
MMBtu
|
$5.40 | |
| Waste Disposal Costs | |||||
| Water Usage | $3,877 | 705 |
Tgal
|
$5.50 | |
| Other Liquid (non-haz) | $179 | 1 |
gal
|
$179.00 | |
| TOTAL YEARLY COSTS | $122,550 | ||||
| RECOMMENDED SAVINGS* | $19,397 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $10,284 | $103,800 |
$10,284
146,910
kWh
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,973 | $6,076 |
$2,973
42,466
kWh
|
|
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $961 | $2,695 |
$961
13,732
kWh
|
|
| 04 | 2.7211: Clean and maintain refrigerant condensers and towers | $5,179 | $4,870 |
$5,179
73,993
kWh
|
|
| TOTAL RECOMMENDED | $19,397 | $117,441 |
$19,397
277,101
kWh
|
||
| TOTAL IMPLEMENTED | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs