Assessment Year | 2025 |
---|---|
Principal Product | Composite aircraft components |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
125,000
ft2
|
Annual Production | 1,920
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $313,073 | 4,113,200 |
kWh
|
$0.076 |
Natural Gas | $17,337 | 5,318 |
MMBtu
|
$3.26 |
TOTAL YEARLY COSTS | $330,410 | |||
RECOMMENDED SAVINGS* | $135,554 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $50,523 | $394,200 |
$50,523
664,774
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,062 | $34,107 |
$13,062
171,871
kWh
|
- | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $2,130 | $5,500 |
$2,130
28,030
kWh
|
- | |
04 | 2.7211: Clean and maintain refrigerant condensers and towers | $16,789 | $15,550 |
$16,789
220,905
kWh
|
- | |
05 | 2.7226: Use computer programs to optimize hvac performance | $42,504 | $114,625 |
$42,504
559,258
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,687 | $7,210 |
$6,687
87,984
kWh
|
- | |
07 | 2.3212: Optimize plant power factor | $3,430 | $12,158 | - | $3,430 | |
08 | 2.6211: Conserve energy by efficient use of vending machines | $429 | $560 |
$429
5,641
kWh
|
- | |
TOTAL RECOMMENDED | $135,554 | $583,910 |
$132,124
1,738,463
kWh
|
$3,430 | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs