ITAC Assessment: OK1153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Hydro-Geothermal Heat Pump Systems
NAICS 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 500
Plant Area 244,850
ft2
Annual Production 7,750
units
Production Hrs. Annual 4,160
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $409,053 7,158,280
kWh
Electricity Demand $172,482 16,910
kW-mo/yr
Natural Gas $55,839 13,016
MMBtu
Waste Disposal Costs
Water Usage $162,691 13,596
Tgal
Water Disposal $35,720 10,618
Tgal
TOTAL YEARLY COSTS $835,785
RECOMMENDED SAVINGS* $75,190 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $61,236 $583,440 $61,236
1,074,308
kWh
-
02 2.3212: Optimize plant power factor $9,017 $11,190 - $9,017
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,133 $5,473 $4,133
72,504
kWh
-
04 2.6211: Conserve energy by efficient use of vending machines $804 $900 $804
14,104
kWh
-
TOTAL RECOMMENDED $75,190 $601,003 $66,173
1,160,916
kWh
$9,017
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs