Assessment Year | 2025 |
---|---|
Principal Product | Lithium ion battery units for electric vehicles |
NAICS | 335912: Primary Battery Manufacturing |
SIC | 3692: Primary Batteries, Dry and Wet |
Sales Range | $500 k to 1M |
# of Employees | 11 |
Plant Area |
104,000
ft2
|
Annual Production | 8,320
units
|
Production Hrs. Annual | 1,920
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $53,777 | 781,910 |
kWh
|
$0.069 | |
Electricity Demand | $185,403 | 15,369 |
kW-mo/yr
|
$12.06 | |
Natural Gas | $3,840 | 702 |
MMBtu
|
$5.47 | |
Waste Disposal Costs | |||||
Water Usage | $554 | 262 |
Tgal
|
$2.11 | |
Water Disposal | $1,636 | 262 |
Tgal
|
$6.24 | |
Other Liquid (non-haz) | $260,000 | 260 |
gal
|
$1,000.00 | |
TOTAL YEARLY COSTS | $505,210 | ||||
RECOMMENDED SAVINGS* | $369,742 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $262 | - |
$262
3,799
kWh
|
- | - | - | |
02 | 2.9114: Use solar heat to make electricty | $100,152 | $858,000 |
$100,152
1,451,471
kWh
|
- | - | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $11,172 | - | - |
$11,172
-
kW-mo/yr
|
- | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $857 | $25,000 |
$583
8,454
kWh
|
- |
$274
-
MMBtu
|
- | |
05 | 3.4146: Change method of deionized water production | $257,299 | $103,000 | - | - | - | $257,299 | |
TOTAL RECOMMENDED | $369,742 | $986,000 |
$100,997
1,463,724
kWh
|
$11,172
-
kW-mo/yr
|
$274
-
MMBtu
|
$257,299 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs