ITAC Assessment: OK1134
ITAC logo
ITAC Assessment: OK1134
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Lithium ion battery units for electric vehicles
NAICS 335912: Primary Battery Manufacturing
SIC 3692: Primary Batteries, Dry and Wet
Sales Range $500
k
to 1
M
# of Employees 11
Plant Area 104,000
ft2
Annual Production 8,320
units
Production Hrs. Annual 1,920
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,777 781,910
kWh
Electricity Demand $185,403 15,369
kW-mo/yr
Natural Gas $3,840 702
MMBtu
Waste Disposal Costs
Water Usage $554 262
Tgal
Water Disposal $1,636 262
Tgal
Other Liquid (non-haz) $260,000 260
gal
TOTAL YEARLY COSTS $505,210
RECOMMENDED SAVINGS* $369,742 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7135: Install occupancy sensors $262 - $262
3,799
kWh
- - -
02 2.9114: Use solar heat to make electricty $100,152 $858,000 $100,152
1,451,471
kWh
- - -
03 2.3132: Recharge batteries on during off-peak demand periods $11,172 - - $11,172
-
kW-mo/yr
- -
04 2.7447: Install vinyl strip / high speed / air curtain doors $857 $25,000 $583
8,454
kWh
- $274
-
MMBtu
-
05 3.4146: Change method of deionized water production $257,299 $103,000 - - - $257,299
TOTAL RECOMMENDED $369,742 $986,000 $100,997
1,463,724
kWh
$11,172
-
kW-mo/yr
$274
-
MMBtu
$257,299
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs