| Assessment Year | 2025 |
|---|---|
| Principal Product | Lithium ion battery units for electric vehicles |
| NAICS | 335912: Primary Battery Manufacturing |
| SIC | 3692: Primary Batteries, Dry and Wet |
| Sales Range | $500 k to 1M |
| # of Employees | 11 |
| Plant Area |
104,000
ft2
|
| Annual Production | 8,320
units
|
| Production Hrs. Annual | 1,920
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $53,777 | 781,910 |
kWh
|
$0.069 | |
| Electricity Demand | $185,403 | 15,369 |
kW-mo/yr
|
$12.06 | |
| Natural Gas | $3,840 | 702 |
MMBtu
|
$5.47 | |
| Waste Disposal Costs | |||||
| Water Usage | $554 | 262 |
Tgal
|
$2.11 | |
| Water Disposal | $1,636 | 262 |
Tgal
|
$6.24 | |
| Other Liquid (non-haz) | $260,000 | 260 |
gal
|
$1,000.00 | |
| TOTAL YEARLY COSTS | $505,210 | ||||
| RECOMMENDED SAVINGS* | $368,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $262 | - |
$262
3,799
kWh
|
- | - | |
| 02 | 2.9114: Use solar heat to make electricty | $100,152 | $858,000 |
$100,152
1,451,471
kWh
|
- | - | |
| 03 | 2.3132: Recharge batteries on during off-peak demand periods | $11,172 | - | - |
$11,172
-
kW-mo/yr
|
- | |
| 04 | 3.4146: Change method of deionized water production | $257,299 | $103,000 |
$(-2,153.0)
(-31,200)
kWh
|
- | $259,452 | |
| TOTAL RECOMMENDED | $368,885 | $961,000 |
$98,261
1,424,070
kWh
|
$11,172
-
kW-mo/yr
|
$259,452 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs