ITAC Assessment: OK1125
ITAC logo
ITAC Assessment: OK1125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Computer Data Storage Systems
NAICS 334112: Computer Storage Device Manufacturing
SIC 3572: Computer Storage Devices
Sales Range $100
M
to 500
M
# of Employees 238
Plant Area 352,000
ft2
Annual Production 594,752
units
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $692,709 9,945,000
kWh
Electricity Demand $131,313 18,035
kW-mo/yr
Natural Gas $64,404 16,151
MMBtu
Waste Disposal Costs
Water Usage $24,779 2,967
Tgal
Water Disposal $4,816 1,079
Tgal
TOTAL YEARLY COSTS $918,021
RECOMMENDED SAVINGS* $95,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.9114: Use solar heat to make electricty $81,240 $643,500 $81,240
1,160,572
kWh
-
02 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $2,279 $62,775 $1,250
17,850
kWh
$1,029
-
MMBtu
03 2.6211: Conserve energy by efficient use of vending machines $2,363 $1,900 $2,363
33,756
kWh
-
04 2.2437: Recover waste heat from equipment $1,664 $8,000 - $1,664
-
MMBtu
05 2.7232: Replace existing hvac unit with high efficiency model $7,917 $55,440 $7,917
113,099
kWh
-
TOTAL RECOMMENDED $95,463 $771,615 $92,770
1,325,277
kWh
$2,693
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs