ITAC Assessment: OK1091
ITAC logo
ITAC Assessment: OK1091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product aircraft parts & part refurbishment
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 292
Plant Area 117,000
ft2
Annual Production 30,000
units
Production Hrs. Annual 3,640
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $357,802 2,819,600
kWh
Natural Gas $5,814 2,741
MMBtu
Waste Disposal Costs
Water Usage $6,484 1,426
Tgal
Water Disposal $13,536 1,426
Tgal
Solid Waste (non-haz) $9,457 925,338
lb
TOTAL YEARLY COSTS $393,093
RECOMMENDED SAVINGS* $110,701 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.7135: Install occupancy sensors $1,017 $630 $1,017
7,826
kWh
-
02 2.7232: Replace existing hvac unit with high efficiency model $3,533 $9,900 $3,533
27,178
kWh
-
03 2.7229: Air condition only space necessary $17,766 - $17,766
136,660
kWh
-
04 2.9114: Use solar heat to make electricty $86,175 $394,200 $86,175
662,888
kWh
-
05 2.3212: Optimize plant power factor $2,210 $9,834 - $2,210
TOTAL RECOMMENDED $110,701 $414,564 $108,491
834,552
kWh
$2,210
TOTAL IMPLEMENTED $6,760 $20,364 $4,550
35,004
kWh
$2,210
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs