Assessment Year | 2022 |
---|---|
Principal Product | Stamped gaskets, fabricated parts, and hoses |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
42,100
ft2
|
Annual Production | 55,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $39,115 | 488,941 |
kWh
|
$0.080 | |
Electricity Demand | $9,072 | 1,586 |
kW-mo/yr
|
$5.72 | |
Electricity Fees | $552 | - |
|
- | |
Natural Gas | $36,464 | 3,942 |
MMBtu
|
$9.25 | |
Waste Disposal Costs | |||||
Water Usage | $2,142 | 451 |
Tgal
|
$4.75 | |
TOTAL YEARLY COSTS | $87,345 | ||||
RECOMMENDED SAVINGS* | $38,145 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $530 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,255 | $7,590 |
$2,734
34,169
kWh
|
$521
-
kW-mo/yr
|
|
02 | 2.9114: Use solar heat to make electricty | $24,215 | $230,880 |
$24,026
300,321
kWh
|
$189
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $530 | $347 |
$530
6,629
kWh
|
- | |
04 | 2.7241: Install outside air damper / economizer on hvac unit | $2,586 | $7,371 |
$2,586
32,323
kWh
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,559 | $9,108 |
$7,559
94,488
kWh
|
- | |
TOTAL RECOMMENDED | $38,145 | $255,296 |
$37,435
467,930
kWh
|
$710
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $530 | $347 |
$530
6,629
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs