Assessment Year | 2022 |
---|---|
Principal Product | Rubber belts for agricultural machinery |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 210 |
Plant Area |
120,000
ft2
|
Annual Production | 8,282,486
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $238,167 | 4,763,332 |
kWh
|
$0.050 | |
Electricity Demand | $255,010 | 11,806 |
kW-mo/yr
|
$21.60 | |
Electricity Fees | $2,964 | - |
|
- | |
Natural Gas | $457,887 | 167,724 |
MMBtu
|
$2.73 | |
Waste Disposal Costs | |||||
Water Usage | $205,361 | 26,028 |
Tgal
|
$7.89 | |
TOTAL YEARLY COSTS | $1,159,389 | ||||
RECOMMENDED SAVINGS* | $63,316 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $19,997 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $32,771 | $39,489 | - | - | $32,771 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,548 | $12,334 |
$10,548
210,961
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,161 | $9,927 |
$9,567
191,338
kWh
|
$5,594
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,707 | $1,176 |
$3,707
74,131
kWh
|
- | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $1,129 | - |
$1,129
22,576
kWh
|
- | - | |
TOTAL RECOMMENDED | $63,316 | $62,926 |
$24,951
499,006
kWh
|
$5,594
-
kW-mo/yr
|
$32,771 | ||
TOTAL IMPLEMENTED | $19,997 | $11,103 |
$14,403
288,045
kWh
|
$5,594
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs