ITAC Assessment: OK1071
ITAC logo
ITAC Assessment: OK1071
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Aeronautical electronic systems
NAICS 334419: Other Electronic Component Manufacturing
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 36,000
ft2
Annual Production 90,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $162,020 1,687,704
kWh
Natural Gas $7,919 738
MMBtu
Waste Disposal Costs
Water Usage $17,569 1,047
Tgal
TOTAL YEARLY COSTS $187,508
RECOMMENDED SAVINGS* $49,098 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,382

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $25,382 $61,013 $25,382
264,395
kWh
- -
02 3.4159: Replace treated water with well / surface water $12,657 $10,000 - $12,657 -
03 2.7144: Install spectral reflectors / delamp $9,419 - $9,419
98,112
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $1,640 - $782
8,142
kWh
- $858
-
MMBtu
TOTAL RECOMMENDED $49,098 $71,013 $35,583
370,649
kWh
$12,657 $858
-
MMBtu
TOTAL IMPLEMENTED $25,382 $61,013 $25,382
264,395
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs