ITAC Assessment: OK1069
ITAC logo
ITAC Assessment: OK1069
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Awards & Recognition Products
NAICS 339999: All Other Miscellaneous Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 320
Plant Area 221,000
ft2
Annual Production 245,336
units
Production Hrs. Annual 2,600
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,920 1,699,244
kWh
Electricity Demand $23,255 2,031
kW-mo/yr
Natural Gas $11,140 2,778
MMBtu
Waste Disposal Costs
Water Usage $5,806 766
Tgal
Water Disposal $3,883 766
Tgal
TOTAL YEARLY COSTS $179,004
RECOMMENDED SAVINGS* $14,433 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,433

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,392 $27,027 $4,685
59,005
kWh
$2,707
-
kW-mo/yr
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,879 - $1,879
23,663
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $612 $304 $612
7,706
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $156 $488 $156
1,966
kWh
-
05 2.7212: Install or upgrade insulation on hvac distribution systems $4,394 $1,540 $4,394
55,342
kWh
-
TOTAL RECOMMENDED $14,433 $29,359 $11,726
147,682
kWh
$2,707
-
kW-mo/yr
TOTAL IMPLEMENTED $14,433 $29,359 $11,726
147,682
kWh
$2,707
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs