ITAC Assessment: OK1068
ITAC logo
ITAC Assessment: OK1068
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Oil & gas field equipment
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $50
M
to 100
M
# of Employees 499
Plant Area 400,000
ft2
Annual Production 387,000
lb
Production Hrs. Annual 5,200
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $572,270 13,308,605
kWh
Electricity Demand $985,076 74,797
kW-mo/yr
Electricity Fees $163,887 -
Natural Gas $51,557 9,934
MMBtu
Waste Disposal Costs
Water Usage $7,232 1,081
Tgal
TOTAL YEARLY COSTS $1,780,022
RECOMMENDED SAVINGS* $16,513 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,122

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $3,103 - $3,103
72,153
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,141 $1,208 $2,141
49,795
kWh
- -
03 2.2449: Recover heat from exhausted steam, hot air or hot water $5,553 $3,192 - - $5,553
-
MMBtu
04 2.7232: Replace existing hvac unit with high efficiency model $3,561 $18,463 $2,165
50,358
kWh
$1,396
-
kW-mo/yr
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $830 - - - $830
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,325 $5,412 $551
12,823
kWh
$774
-
kW-mo/yr
-
TOTAL RECOMMENDED $16,513 $28,275 $7,960
185,129
kWh
$2,170
-
kW-mo/yr
$6,383
-
MMBtu
TOTAL IMPLEMENTED $12,122 $9,812 $5,795
134,771
kWh
$774
-
kW-mo/yr
$5,553
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs