| Assessment Year | 2022 |
|---|---|
| Principal Product | plastic and metallic pipe fittings |
| NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
| SIC | 3084: Plastics Pipe |
| Sales Range | $100 M to 500M |
| # of Employees | 620 |
| Plant Area |
312,500
ft2
|
| Annual Production | 7,500,000
units
|
| Production Hrs. Annual | 8,688
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $655,074 | 15,234,280 |
kWh
|
$0.043 | |
| Electricity Demand | $190,452 | 31,742 |
kW-mo/yr
|
$6.00 | |
| Electricity Fees | $1,896 | - |
|
- | |
| Natural Gas | $107,896 | 34,805 |
MMBtu
|
$3.10 | |
| Waste Disposal Costs | |||||
| Water Usage | $20,885 | 4,641 |
Tgal
|
$4.50 | |
| TOTAL YEARLY COSTS | $976,203 | ||||
| RECOMMENDED SAVINGS* | $54,042 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $54,042 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $2,073 | $12,233 |
$1,305
30,350
kWh
|
$768
-
kW-mo/yr
|
|
| 02 | 2.4239: Eliminate or reduce compressed air usage | $29,263 | - |
$29,263
680,531
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,433 | $2,429 |
$8,433
196,106
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,273 | $21,539 |
$11,969
278,337
kWh
|
$2,304
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $54,042 | $36,201 |
$50,970
1,185,324
kWh
|
$3,072
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $54,042 | $36,201 |
$50,970
1,185,324
kWh
|
$3,072
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs