ITAC Assessment: OK1058
ITAC logo
ITAC Assessment: OK1058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product treated wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 20
Plant Area 360,000
ft2
Annual Production 1,560,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,396 1,313,200
kWh
Electricity Demand $23,933 3,338
kW-mo/yr
Natural Gas $3,644 439
MMBtu
Waste Disposal Costs
Water Usage $58,106 17,090
Tgal
TOTAL YEARLY COSTS $125,079
RECOMMENDED SAVINGS* $9,692 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,437

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $1,800 $3,000 - - $1,800
02 2.7142: Utilize higher efficiency lamps and/or ballasts $455 $2,130 $455
15,154
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,252 $7,778 $7,252
241,745
kWh
- -
04 2.7232: Replace existing hvac unit with high efficiency model $185 $700 $131
4,380
kWh
$54
-
kW-mo/yr
-
TOTAL RECOMMENDED $9,692 $13,608 $7,838
261,279
kWh
$54
-
kW-mo/yr
$1,800
TOTAL IMPLEMENTED $7,437 $8,478 $7,383
246,125
kWh
$54
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs