| Assessment Year | 2021 |
|---|---|
| Principal Product | treated wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $5 M to 10M |
| # of Employees | 20 |
| Plant Area |
360,000
ft2
|
| Annual Production | 1,560,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $39,396 | 1,313,200 |
kWh
|
$0.030 | |
| Electricity Demand | $23,933 | 3,338 |
kW-mo/yr
|
$7.17 | |
| Natural Gas | $3,644 | 439 |
MMBtu
|
$8.30 | |
| Waste Disposal Costs | |||||
| Water Usage | $58,106 | 17,090 |
Tgal
|
$3.40 | |
| TOTAL YEARLY COSTS | $125,079 | ||||
| RECOMMENDED SAVINGS* | $9,692 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $7,437 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $1,800 | $3,000 | - | - | $1,800 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $455 | $2,130 |
$455
15,154
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,252 | $7,778 |
$7,252
241,745
kWh
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $185 | $700 |
$131
4,380
kWh
|
$54
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $9,692 | $13,608 |
$7,838
261,279
kWh
|
$54
-
kW-mo/yr
|
$1,800 | ||
| TOTAL IMPLEMENTED | $7,437 | $8,478 |
$7,383
246,125
kWh
|
$54
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs