ITAC Assessment: OK1050
ITAC logo
ITAC Assessment: OK1050
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Plastic Products Manufacturing Machinery
NAICS 339999: All Other Miscellaneous Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 79
Plant Area 60,000
ft2
Annual Production 500,000
lb
Production Hrs. Annual 4,896
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,114 425,953
kWh
Electricity Demand $68,415 5,491
kW-mo/yr
Electricity Fees $1,127 -
Natural Gas $8,485 955
MMBtu
Waste Disposal Costs
Water Usage $2,473 284
Tgal
TOTAL YEARLY COSTS $131,614
RECOMMENDED SAVINGS* $6,466 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,327 - $2,327
19,388
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,760 $900 $1,760
14,664
kWh
-
03 2.3212: Optimize plant power factor $2,379 $1,973 - $2,379
TOTAL RECOMMENDED $6,466 $2,873 $4,087
34,052
kWh
$2,379
TOTAL IMPLEMENTED $1,760 $900 $1,760
14,664
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs