Assessment Year | 2021 |
---|---|
Principal Product | Architectural Glass |
NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
130,000
ft2
|
Annual Production | 7,500,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $594,765 | 9,293,200 |
kWh
|
$0.064 | |
Electricity Demand | $181,666 | 25,337 |
kW-mo/yr
|
$7.17 | |
Natural Gas | $6,656 | 1,698 |
MMBtu
|
$3.92 | |
Waste Disposal Costs | |||||
Water Usage | $22,077 | 3,654 |
Tgal
|
$6.04 | |
TOTAL YEARLY COSTS | $805,164 | ||||
RECOMMENDED SAVINGS* | $9,901 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,742 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $5,159 | $6,000 | - | - | $5,159 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $552 | $820 |
$414
6,466
kWh
|
$138
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,589 | - |
$1,589
24,827
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,601 | $1,060 |
$2,601
40,635
kWh
|
- | - | |
TOTAL RECOMMENDED | $9,901 | $7,880 |
$4,604
71,928
kWh
|
$138
-
kW-mo/yr
|
$5,159 | ||
TOTAL IMPLEMENTED | $4,742 | $1,880 |
$4,604
71,928
kWh
|
$138
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs