| Assessment Year | 2021 |
|---|---|
| Principal Product | Synthetic petroleum based polymers |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2999: Products of Petroleum and Coal, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 95 |
| Plant Area |
190,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $662,185 | 13,243,690 |
kWh
|
$0.050 | |
| Electricity Demand | $182,885 | 25,507 |
kW-mo/yr
|
$7.17 | |
| Natural Gas | $987,834 | 371,366 |
MMBtu
|
$2.66 | |
| Waste Disposal Costs | |||||
| Water Usage | $139,034 | 15,414 |
Tgal
|
$9.02 | |
| TOTAL YEARLY COSTS | $1,971,938 | ||||
| RECOMMENDED SAVINGS* | $71,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $47,773 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $37,041 | $2,860 | - | - | - |
$37,041
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,475 | $13,356 |
$8,475
169,494
kWh
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $2,257 | $3,150 |
$1,500
29,994
kWh
|
$757
-
kW-mo/yr
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,153 | $4,000 |
$1,153
23,058
kWh
|
- | - | - | |
| 05 | 2.3212: Optimize plant power factor | $22,294 | $15,000 | - | - | $22,294 | - | |
| TOTAL RECOMMENDED | $71,220 | $38,366 |
$11,128
222,546
kWh
|
$757
-
kW-mo/yr
|
$22,294 |
$37,041
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $47,773 | $19,366 |
$9,975
199,488
kWh
|
$757
-
kW-mo/yr
|
- |
$37,041
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs