ITAC Assessment: OK1028
ITAC logo
ITAC Assessment: OK1028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product carbonated beverages
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 152,000
ft2
Annual Production 48,000
Tgal
Production Hrs. Annual 7,488
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $556,784 11,248,191
kWh
Electricity Demand $151,971 27,400
kW-mo/yr
Natural Gas $89,196 24,132
MMBtu
TOTAL YEARLY COSTS $797,951
RECOMMENDED SAVINGS* $13,025 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $5,729 $1,500 - - $5,729
-
MMBtu
02 2.2425: Use flue gases to heat process or service water $2,193 $3,750 - - $2,193
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,990 $3,313 $1,704
34,784
kWh
$286
-
kW-mo/yr
-
04 2.2511: Insulate bare equipment $53 $111 $53
1,074
kWh
- -
05 2.7232: Replace existing hvac unit with high efficiency model $2,802 $8,260 $2,802
57,188
kWh
- -
06 2.6218: Turn off equipment when not in use $258 $616 $258
5,263
kWh
- -
TOTAL RECOMMENDED $13,025 $17,550 $4,817
98,309
kWh
$286
-
kW-mo/yr
$7,922
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs