ITAC Assessment: OK1023
ITAC logo
ITAC Assessment: OK1023
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Re-manufactured Engines and Transmissions
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 95
Plant Area 166,750
ft2
Annual Production 960
units
Production Hrs. Annual 3,432
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,686 908,840
kWh
Electricity Demand $21,398 1,337
kW-mo/yr
Electricity Fees $1,902 -
Natural Gas $46,577 13,959
MMBtu
Waste Disposal Costs
Water Usage $1,448 464
Tgal
TOTAL YEARLY COSTS $118,011
RECOMMENDED SAVINGS* $14,044 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $770 - $770
15,101
kWh
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,606 $4,736 $1,606
31,485
kWh
- - -
03 2.3212: Optimize plant power factor $464 $1,236 - - $464 -
04 2.7231: Use radiant heater for spot heating $915 $3,252 - - - $915
-
MMBtu
05 2.7211: Clean and maintain refrigerant condensers and towers $415 $538 $357
6,994
kWh
$58
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,874 $15,402 $4,709
92,334
kWh
$5,165
-
kW-mo/yr
- -
TOTAL RECOMMENDED $14,044 $25,164 $7,442
145,914
kWh
$5,223
-
kW-mo/yr
$464 $915
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs