| Assessment Year | 2019 |
|---|---|
| Principal Product | purified water |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 5 |
| Plant Area |
35,000
ft2
|
| Annual Production | 5,079,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,511 | 1,671,000 |
kWh
|
$0.041 |
| Electricity Demand | $77,314 | 3,975 |
kW-mo/yr
|
$19.45 |
| Electricity Fees | $5,891 | - |
|
- |
| Natural Gas | $10,159 | 2,099 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | $161,875 | |||
| RECOMMENDED SAVINGS* | $10,632 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,661 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $3,856 | $17,056 | - | - | $3,856 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,072 | $9,350 |
$2,847
69,440
kWh
|
$1,225
-
kW-mo/yr
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,709 | $2,600 |
$1,709
41,671
kWh
|
- | - | - | |
| 04 | 2.7241: Install outside air damper / economizer on hvac unit | $262 | $1,320 |
$262
6,385
kWh
|
- | - | - | |
| 05 | 2.7211: Clean and maintain refrigerant condensers and towers | $392 | $155 |
$120
2,923
kWh
|
$272
-
kW-mo/yr
|
- | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $341 | - |
$249
6,075
kWh
|
- | - |
$92
-
MMBtu
|
|
| TOTAL RECOMMENDED | $10,632 | $30,481 |
$5,187
126,494
kWh
|
$1,497
-
kW-mo/yr
|
$3,856 |
$92
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $8,661 | $26,561 |
$3,216
78,438
kWh
|
$1,497
-
kW-mo/yr
|
$3,856 |
$92
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs