| Assessment Year | 2019 |
|---|---|
| Principal Product | bio-solid |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 62 |
| Plant Area |
233,243
ft2
|
| Annual Production | 4,800
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $840,480 | 21,012,000 |
kWh
|
$0.040 |
| Electricity Demand | $641,779 | 34,560 |
kW-mo/yr
|
$18.57 |
| Electricity Fees | $41,606 | - |
|
- |
| Natural Gas | $107,961 | 27,471 |
MMBtu
|
$3.93 |
| TOTAL YEARLY COSTS | $1,631,826 | |||
| RECOMMENDED SAVINGS* | $243,187 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $127,275 | $96,138 |
$127,275
3,181,876
kWh
|
- | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,747 | $27,232 |
$11,747
293,686
kWh
|
- | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,742 | $13,761 |
$11,742
293,543
kWh
|
- | - | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $7,674 | $34,500 |
$7,674
191,844
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $59,363 | $100,260 |
$40,548
1,013,695
kWh
|
$18,815
-
kW-mo/yr
|
- | - | |
| 06 | 2.3212: Optimize plant power factor | $20,771 | $24,531 | - | - | $20,771 | - | |
| 07 | 2.7241: Install outside air damper / economizer on hvac unit | $1,218 | $5,291 |
$1,218
30,439
kWh
|
- | - | - | |
| 08 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,015 | $548 |
$310
7,751
kWh
|
$705
-
kW-mo/yr
|
- | - | |
| 09 | 2.7224: Reduce space conditioning during non-working hours | $913 | - |
$649
16,236
kWh
|
- | - |
$264
-
MMBtu
|
|
| 10 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,469 | $300 | - | - | - |
$1,469
-
MMBtu
|
|
| TOTAL RECOMMENDED | $243,187 | $302,561 |
$201,163
5,029,070
kWh
|
$19,520
-
kW-mo/yr
|
$20,771 |
$1,733
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs