Assessment Year | 2019 |
---|---|
Principal Product | Frozen food |
NAICS | 311412: Frozen Specialty Food Manufacturing |
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 319 |
Plant Area |
600,000
ft2
|
Annual Production | 115,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,392,395 | 30,347,477 |
kWh
|
$0.046 | |
Electricity Demand | $890,991 | 75,470 |
kW-mo/yr
|
$11.81 | |
Natural Gas | $305,796 | 46,123 |
MMBtu
|
$6.63 | |
Waste Disposal Costs | |||||
Water Usage | $160,649 | 65,296 |
Tgal
|
$2.46 | |
TOTAL YEARLY COSTS | $2,749,831 | ||||
RECOMMENDED SAVINGS* | $14,933 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $6,732 | $6,990 | - |
$6,732
-
MMBtu
|
|
02 | 2.1116: Improve combustion control capability | $5,516 | $18,500 | - |
$5,516
-
MMBtu
|
|
03 | 2.7135: Install occupancy sensors | $255 | $1,132 |
$255
5,541
kWh
|
- | |
04 | 2.7211: Clean and maintain refrigerant condensers and towers | $679 | $1,295 |
$679
14,752
kWh
|
- | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $1,751 | $8,520 |
$1,751
38,066
kWh
|
- | |
TOTAL RECOMMENDED | $14,933 | $36,437 |
$2,685
58,359
kWh
|
$12,248
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs