ITAC Assessment: OK1004
ITAC logo
ITAC Assessment: OK1004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Frozen food
NAICS 311412: Frozen Specialty Food Manufacturing
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 319
Plant Area 600,000
ft2
Annual Production 115,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,392,395 30,347,477
kWh
Electricity Demand $890,991 75,470
kW-mo/yr
Natural Gas $305,796 46,123
MMBtu
Waste Disposal Costs
Water Usage $160,649 65,296
Tgal
TOTAL YEARLY COSTS $2,749,831
RECOMMENDED SAVINGS* $14,933 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $6,732 $6,990 - $6,732
-
MMBtu
02 2.1116: Improve combustion control capability $5,516 $18,500 - $5,516
-
MMBtu
03 2.7135: Install occupancy sensors $255 $1,132 $255
5,541
kWh
-
04 2.7211: Clean and maintain refrigerant condensers and towers $679 $1,295 $679
14,752
kWh
-
05 2.7241: Install outside air damper / economizer on hvac unit $1,751 $8,520 $1,751
38,066
kWh
-
TOTAL RECOMMENDED $14,933 $36,437 $2,685
58,359
kWh
$12,248
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs