Assessment Year | 2019 |
---|---|
Principal Product | Roofing Shingle Substrate |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $10 M to 50M |
# of Employees | 77 |
Plant Area |
70,000
ft2
|
Annual Production | 263,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $638,456 | 13,164,000 |
kWh
|
$0.049 | |
Electricity Demand | $204,905 | 22,959 |
kW-mo/yr
|
$8.92 | |
Natural Gas | $1,077,552 | 256,296 |
MMBtu
|
$4.20 | |
Waste Disposal Costs | |||||
Water Usage | $32,439 | 10,868 |
Tgal
|
$2.98 | |
TOTAL YEARLY COSTS | $1,953,352 | ||||
RECOMMENDED SAVINGS* | $265,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $13,594 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $20,293 | $28,306 | - | - | $20,293 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,343 | $2,609 |
$5,864
120,941
kWh
|
$1,479
-
kW-mo/yr
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $2,400 | $2,933 | - | - | - |
$2,400
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,768 | $3,646 |
$2,768
57,070
kWh
|
- | - | - | |
05 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $191,600 | $806,420 |
$138,080
2,847,000
kWh
|
$53,520
-
kW-mo/yr
|
- | - | |
06 | 2.6232: Install set-back timers | $1,083 | $802 |
$457
9,431
kWh
|
- | - |
$626
-
MMBtu
|
|
07 | 2.7231: Use radiant heater for spot heating | $39,703 | $37,000 | - | - | - |
$39,703
-
MMBtu
|
|
TOTAL RECOMMENDED | $265,190 | $881,716 |
$147,169
3,034,442
kWh
|
$54,999
-
kW-mo/yr
|
$20,293 |
$42,729
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,594 | $9,990 |
$9,089
187,442
kWh
|
$1,479
-
kW-mo/yr
|
- |
$3,026
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs