ITAC Assessment: OK0988
ITAC logo
ITAC Assessment: OK0988
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product pizza crust
NAICS 311813: Frozen Cakes, Pies, and Other Pastries Manufacturing
SIC 2053: Frozen Bakery Products, Except Bread
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 80,000
ft2
Annual Production 9,906,066
lb
Production Hrs. Annual 5,460
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,776 3,481,435
kWh
Electricity Demand $58,111 9,734
kW-mo/yr
Electricity Fees $4,125 -
Natural Gas $12,181 2,627
MMBtu
TOTAL YEARLY COSTS $210,193
RECOMMENDED SAVINGS* $21,332 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $7,394 $12,000 - - $7,394 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $739 $2,330 $739
18,942
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,279 $15,642 $6,201
158,995
kWh
$2,078
-
kW-mo/yr
- -
04 2.9112: Use solar heat to heat water $4,920 $155,149 - - - $4,920
-
MMBtu
TOTAL RECOMMENDED $21,332 $185,121 $6,940
177,937
kWh
$2,078
-
kW-mo/yr
$7,394 $4,920
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs