ITAC Assessment: OK0978
ITAC logo
ITAC Assessment: OK0978
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product paint and coating
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 220,000
ft2
Annual Production 8,000
Tgal
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,635 7,551,960
kWh
Electricity Demand $344,993 17,639
kW-mo/yr
Natural Gas $87,595 18,549
MMBtu
TOTAL YEARLY COSTS $730,223
RECOMMENDED SAVINGS* $90,964 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $18,551 $40,582 - - $18,551 -
02 2.2414: Use waste heat from hot flue gases to preheat $4,546 $20,000 - - - $4,546
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $2,233 $2,000 - - - $2,233
-
MMBtu
04 2.1233: Analyze flue gas for proper air/fuel ratio $988 $4,800 - - - $988
-
MMBtu
05 2.2437: Recover waste heat from equipment $7,833 $2,777 - - - $7,833
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,519 $410 $1,519
38,955
kWh
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $27,821 $74,753 $27,821
713,362
kWh
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $5,821 $27,209 $2,816
72,206
kWh
$3,005
-
kW-mo/yr
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,046 $1,446 $484
12,400
kWh
$562
-
kW-mo/yr
- -
10 2.3132: Recharge batteries on during off-peak demand periods $19,215 - - $19,215
-
kW-mo/yr
- -
11 2.7232: Replace existing hvac unit with high efficiency model $1,391 $3,600 $538
13,797
kWh
$853
-
kW-mo/yr
- -
TOTAL RECOMMENDED $90,964 $177,577 $33,178
850,720
kWh
$23,635
-
kW-mo/yr
$18,551 $15,600
-
MMBtu
TOTAL IMPLEMENTED $9,100 $30,655 $3,300
84,606
kWh
$3,567
-
kW-mo/yr
- $2,233
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs