Assessment Year | 2017 |
---|---|
Principal Product | Fluid transfer pumps & meters |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $50 M to 100M |
# of Employees | 210 |
Plant Area |
174,000
ft2
|
Annual Production | 400,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,312 | 1,755,818 |
kWh
|
$0.042 |
Electricity Demand | $128,035 | 6,114 |
kW-mo/yr
|
$20.94 |
Electricity Fees | $1,200 | - |
|
- |
Natural Gas | $5,650 | 845 |
MMBtu
|
$6.69 |
TOTAL YEARLY COSTS | $208,197 | |||
RECOMMENDED SAVINGS* | $33,751 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $12,407 | $15,373 | - | - | $12,407 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,219 | $12,710 |
$1,785
42,501
kWh
|
$3,434
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,588 | $7,868 |
$881
20,987
kWh
|
$3,707
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,524 | $11,407 |
$1,304
31,051
kWh
|
$2,220
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,726 | - |
$2,726
64,896
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $975 | $691 |
$975
23,209
kWh
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $414 | - |
$414
9,859
kWh
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $309 | $191 |
$309
7,363
kWh
|
- | - | |
09 | 2.7232: Replace existing hvac unit with high efficiency model | $3,589 | $11,640 |
$1,118
26,620
kWh
|
$2,471
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $33,751 | $59,880 |
$9,512
226,486
kWh
|
$11,832
-
kW-mo/yr
|
$12,407 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs