| Assessment Year | 2017 |
|---|---|
| Principal Product | Fluid transfer pumps & meters |
| NAICS | 333911: Pump and Pumping Equipment Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 210 |
| Plant Area |
174,000
ft2
|
| Annual Production | 400,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $73,312 | 1,755,818 |
kWh
|
$0.042 |
| Electricity Demand | $128,035 | 6,114 |
kW-mo/yr
|
$20.94 |
| Electricity Fees | $1,200 | - |
|
- |
| Natural Gas | $5,650 | 845 |
MMBtu
|
$6.69 |
| TOTAL YEARLY COSTS | $208,197 | |||
| RECOMMENDED SAVINGS* | $33,751 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $12,407 | $15,373 | - | - | $12,407 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,219 | $12,710 |
$1,785
42,501
kWh
|
$3,434
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,588 | $7,868 |
$881
20,987
kWh
|
$3,707
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,524 | $11,407 |
$1,304
31,051
kWh
|
$2,220
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,726 | - |
$2,726
64,896
kWh
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $975 | $691 |
$975
23,209
kWh
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $414 | - |
$414
9,859
kWh
|
- | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $309 | $191 |
$309
7,363
kWh
|
- | - | |
| 09 | 2.7232: Replace existing hvac unit with high efficiency model | $3,589 | $11,640 |
$1,118
26,620
kWh
|
$2,471
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $33,751 | $59,880 |
$9,512
226,486
kWh
|
$11,832
-
kW-mo/yr
|
$12,407 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs