Assessment Year | 2017 |
---|---|
Principal Product | Oil field equipment |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | greater than $500 M |
# of Employees | 635 |
Plant Area |
727,191
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $687,451 | 25,461,155 |
kWh
|
$0.027 |
Electricity Demand | $417,116 | 107,546 |
kW-mo/yr
|
$3.88 |
Natural Gas | $748,631 | 119,781 |
MMBtu
|
$6.25 |
TOTAL YEARLY COSTS | $1,853,198 | |||
RECOMMENDED SAVINGS* | $337,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $201,958 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $125,000 | $442,000 | - | - | - |
$125,000
-
MMBtu
|
|
02 | 2.8115: Base utility charges on usage rather than area occupied | $113,700 | $24,000 | - | - | $113,700 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $74,450 | $305,694 |
$49,270
1,824,833
kWh
|
$25,180
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,526 | $21,137 |
$2,335
86,468
kWh
|
$1,191
-
kW-mo/yr
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $7,886 | - |
$5,800
214,893
kWh
|
$2,086
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,570 | $17,250 |
$6,570
243,310
kWh
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,676 | $17,550 |
$3,676
136,172
kWh
|
- | - | - | |
08 | 2.2514: Cover open tanks | $2,956 | $1,250 | - | - | - |
$2,956
-
MMBtu
|
|
09 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $36 | $100 | - | - | - |
$36
-
MMBtu
|
|
TOTAL RECOMMENDED | $337,800 | $828,981 |
$67,651
2,505,676
kWh
|
$28,457
-
kW-mo/yr
|
$113,700 |
$127,992
-
MMBtu
|
||
TOTAL IMPLEMENTED | $201,958 | $385,731 |
$61,851
2,290,783
kWh
|
$26,371
-
kW-mo/yr
|
$113,700 |
$36
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs