ITAC Assessment: OK0957
ITAC logo
ITAC Assessment: OK0957
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Salt
NAICS 212399: All Other Nonmetallic Mineral Mining
SIC 1479: Chemical and Fertilizer Mineral Mining, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 56
Plant Area 440,000
ft2
Annual Production 500,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $155,809 4,097,600
kWh
Electricity Demand $283,826 14,798
kW-mo/yr
Natural Gas $45,607 10,648
MMBtu
TOTAL YEARLY COSTS $485,242
RECOMMENDED SAVINGS* $43,854 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,767

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,200 $2,994 $816
21,474
kWh
$384
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $890 $1,320 $449
11,825
kWh
$441
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,710 $2,100 $4,710
123,947
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,025 - $2,025
53,290
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,973 $8,747 $6,973
183,505
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,059 $52,806 $18,059
475,224
kWh
-
07 2.4133: Use most efficient type of electric motors $9,997 $29,582 $2,172
57,149
kWh
$7,825
-
kW-mo/yr
TOTAL RECOMMENDED $43,854 $97,549 $35,204
926,414
kWh
$8,650
-
kW-mo/yr
TOTAL IMPLEMENTED $31,767 $63,653 $31,767
835,966
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs