Assessment Year | 2016 |
---|---|
Principal Product | Coated aluminum, smart levels |
NAICS | 332510: Hardware Manufacturing |
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
300,000
ft2
|
Annual Production | 500,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $268,076 | 4,813,498 |
kWh
|
$0.056 | |
Electricity Demand | $79,626 | 13,727 |
kW-mo/yr
|
$5.80 | |
Natural Gas | $92,264 | 24,039 |
MMBtu
|
$3.84 | |
Waste Disposal Costs | |||||
Water Usage | $97,000 | 13,193 |
Tgal
|
$7.35 | |
TOTAL YEARLY COSTS | $536,966 | ||||
RECOMMENDED SAVINGS* | $131,590 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $17,826 | $50,400 |
$14,903
266,129
kWh
|
$2,923
-
kW-mo/yr
|
- | - | - | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,613 | $3,847 |
$5,613
100,236
kWh
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,319 | $5,020 |
$1,319
23,559
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $720 | $1,313 |
$720
12,854
kWh
|
- | - | - | - | |
05 | 2.1212: Operate boilers on high fire setting | $10,228 | $44,000 | - | - | - |
$10,228
-
MMBtu
|
- | |
06 | 2.2514: Cover open tanks | $9,702 | $850 | - | - | - |
$9,702
-
MMBtu
|
- | |
07 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $74,759 | $284,084 |
$117,411
2,096,640
kWh
|
$19,488
-
kW-mo/yr
|
- |
$(-41,174.0)
-
MMBtu
|
$(-20,966.0) | |
08 | 2.3212: Optimize plant power factor | $11,423 | $30,600 | - | - | $11,423 | - | - | |
TOTAL RECOMMENDED | $131,590 | $420,114 |
$139,966
2,499,418
kWh
|
$22,411
-
kW-mo/yr
|
$11,423 |
$(-21,244.0)
-
MMBtu
|
$(-20,966.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs