ITAC Assessment: OK0914
ITAC logo
ITAC Assessment: OK0914
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Poultry processing
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range greater than $500
M
# of Employees 3,500
Plant Area 500,000
ft2
Annual Production 1,524,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,107,091 128,458,035
kWh
Electricity Demand $1,486,899 250,284
kW-mo/yr
Natural Gas $6,617,751 1,410,023
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $572,952 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,624

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $4,502 $11,500 - - - $4,502
-
MMBtu
02 2.1233: Analyze flue gas for proper air/fuel ratio $7,411 $32,000 - - - $7,411
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $4,010 $2,099 - - - $4,010
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,766 $7,337 $1,246
31,146
kWh
$520
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,014 $18,774 $3,159
78,963
kWh
$855
-
kW-mo/yr
- -
06 2.6218: Turn off equipment when not in use $13,124 $200 $13,124
328,104
kWh
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,340 $3,200 $15,340
383,503
kWh
- - -
08 2.2437: Recover waste heat from equipment $42,247 $75,023 - - - $42,247
-
MMBtu
09 2.2414: Use waste heat from hot flue gases to preheat $22,289 $11,500 - - - $22,289
-
MMBtu
10 2.1233: Analyze flue gas for proper air/fuel ratio $9,732 $17,000 - - - $9,732
-
MMBtu
11 2.2136: Install / repair insulation on steam lines $3,699 $876 - - - $3,699
-
MMBtu
12 2.7142: Utilize higher efficiency lamps and/or ballasts $1,749 $7,233 $1,236
30,888
kWh
$513
-
kW-mo/yr
- -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $1,780 $7,450 $1,438
35,942
kWh
$342
-
kW-mo/yr
- -
14 2.6218: Turn off equipment when not in use $2,544 $200 $2,544
63,600
kWh
- - -
15 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,284 $1,600 $6,284
157,107
kWh
- - -
16 2.2437: Recover waste heat from equipment $64,892 $80,198 - - - $64,892
-
MMBtu
17 2.2136: Install / repair insulation on steam lines $3,733 $703 - - - $3,733
-
MMBtu
18 2.7142: Utilize higher efficiency lamps and/or ballasts $2,019 $7,450 $1,677
41,933
kWh
$342
-
kW-mo/yr
- -
19 2.7142: Utilize higher efficiency lamps and/or ballasts $1,048 $5,892 $741
18,533
kWh
$307
-
kW-mo/yr
- -
20 2.3212: Optimize plant power factor $52,725 $154,000 - - $52,725 -
21 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $308,044 $1,832,665 - - $226,809 $81,235
-
MMBtu
TOTAL RECOMMENDED $572,952 $2,276,900 $46,789
1,169,719
kWh
$2,880
-
kW-mo/yr
$279,534 $243,750
-
MMBtu
TOTAL IMPLEMENTED $21,624 $4,800 $21,624
540,610
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs