| Assessment Year | 2022 |
|---|---|
| Principal Product | Plywood |
| NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
| SIC | 2436: Softwood Veneer and Plywood |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
510,000
ft2
|
| Annual Production | 1,333,333
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $3,654,999 | 63,709,884 |
kWh
|
$0.057 |
| Electricity Demand | $523,538 | 101,360 |
kW-mo/yr
|
$5.17 |
| Electricity Fees | $158,757 | - |
|
- |
| Natural Gas | $4,659,736 | 971,793 |
MMBtu
|
$4.79 |
| TOTAL YEARLY COSTS | $8,997,030 | |||
| RECOMMENDED SAVINGS* | $779,294 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $94,327 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $19,881 | $1,000 |
$17,415
303,397
kWh
|
$1,738
-
kW-mo/yr
|
$728 | - | |
| 02 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $3,710 | $1,651 |
$3,071
53,506
kWh
|
$522
-
kW-mo/yr
|
$117 | - | |
| 03 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $429,299 | $2,825,211 |
$340,551
5,932,943
kWh
|
$73,032
-
kW-mo/yr
|
$15,716 | - | |
| 04 | 2.2442: Preheat combustion air with waste heat | $230,787 | $328,350 | - | - | - |
$230,787
-
MMBtu
|
|
| 05 | 2.3212: Optimize plant power factor | $90,617 | $35,347 | - | - | $90,617 | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,000 | $1,784 |
$3,973
69,228
kWh
|
$844
-
kW-mo/yr
|
$183 | - | |
| TOTAL RECOMMENDED | $779,294 | $3,193,343 |
$365,010
6,359,074
kWh
|
$76,136
-
kW-mo/yr
|
$107,361 |
$230,787
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $94,327 | $36,998 |
$3,071
53,506
kWh
|
$522
-
kW-mo/yr
|
$90,734 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs