ITAC Assessment: OK0911
ITAC logo
ITAC Assessment: OK0911
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Medium Density Fiberboards
NAICS 322130: Paperboard Mills
SIC 2631: Paperboard Mills
Sales Range $1
M
to 5
M
# of Employees 131
Plant Area 167,760
ft2
Annual Production 70,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,862,872 33,265,570
kWh
Electricity Demand $88,412 76,217
kW-mo/yr
Natural Gas $1,673,972 378,326
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $683,804 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,424

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Wood Savings Water Disposal Savings Water Consumption Savings
01 2.1116: Improve combustion control capability $14,334 $41,000 - - $14,334
-
MMBtu
- - -
02 2.2135: Repair and eliminate steam leaks $7,790 $400 - - $7,790
-
MMBtu
- - -
03 2.2136: Install / repair insulation on steam lines $12,634 $2,848 - - $12,634
-
MMBtu
- - -
04 2.1224: Replace boiler $501,021 $1,650,000 - - $611,021
-
MMBtu
$(-110,000.0)
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,030 $3,797 $1,030
17,303
kWh
- - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,343 $37,638 $9,014
160,967
kWh
$329
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,129 $4,880 $1,129
20,153
kWh
- - - - -
08 3.4151: Minimize water usage $136,438 $968,000 - - - - $97,456
-
Tgal
$38,982
-
Tgal
09 2.6211: Conserve energy by efficient use of vending machines $85 $420 $85
1,508
kWh
- - - - -
TOTAL RECOMMENDED $683,804 $2,708,983 $11,258
199,931
kWh
$329
-
kW-mo/yr
$645,779
-
MMBtu
$(-110,000.0)
-
MMBtu
$97,456
-
Tgal
$38,982
-
Tgal
TOTAL IMPLEMENTED $20,424 $3,248 - - $20,424
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Wood Savings Water Disposal Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs