ITAC Assessment: OK0897
ITAC logo
ITAC Assessment: OK0897
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Hydraulic lift tables for material handling
NAICS 333923: Overhead Traveling Crane, Hoist, and Monorail System Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 114,750
ft2
Annual Production 20,000
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,955 1,626,720
kWh
Electricity Demand $43,998 5,378
kW-mo/yr
Natural Gas $39,370 5,124
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,877 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,877

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $5,056 - - - $5,056
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,440 $1,188 $2,440
52,944
kWh
- -
03 2.2437: Recover waste heat from equipment $2,796 $2,066 - $2,796
-
MMBtu
-
04 2.6242: Minimize operation of equipment maintained in standby condition $248 - $248
5,375
kWh
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,000 $10,067 $3,000
65,075
kWh
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,792 $1,656 $2,792
60,570
kWh
- -
07 2.7232: Replace existing hvac unit with high efficiency model $13,545 $3,641 - $13,545
-
MMBtu
-
TOTAL RECOMMENDED $29,877 $18,618 $8,480
183,964
kWh
$16,341
-
MMBtu
$5,056
TOTAL IMPLEMENTED $29,877 $18,618 $8,480
183,964
kWh
$16,341
-
MMBtu
$5,056
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs