ITAC Assessment: OK0857
ITAC logo
ITAC Assessment: OK0857
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Cattle feed
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 55,000
ft2
Annual Production 80,000
units
Production Hrs. Annual 3,520
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,852 2,910,400
kWh
Electricity Demand $29,012 11,970
kW-mo/yr
Natural Gas $24,345 4,370
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,232 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $46,232 $492,750 $113,062
1,284,800
kWh
$10,600
-
kW-mo/yr
$(-17,987.0) $(-59,443.0)
-
MMBtu
TOTAL RECOMMENDED $46,232 $492,750 $113,062
1,284,800
kWh
$10,600
-
kW-mo/yr
$(-17,987.0) $(-59,443.0)
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs