| Assessment Year | 1989 |
|---|---|
| Principal Product | DENIM JEANS |
| NAICS |
n/a
|
| SIC | 2325: Men's and Boys' Separate Trousers and Slacks |
| Sales Range | $50 M to 100M |
| # of Employees | 265 |
| Plant Area |
n/a
|
| Annual Production | 1,900,000
pieces
|
| Production Hrs. Annual | 5,400
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $100,913 | 1,785,756 |
kWh
|
$0.057 |
| Natural Gas | $78,372 | 21,012 |
MMBtu
|
$3.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,683 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,514 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $421 | $121 |
$421
7,327
kWh
|
- | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $447 | $250 |
$447
7,913
kWh
|
- | - | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $315 | $150 |
$315
5,569
kWh
|
- | - | |
| 04 | 2.2113: Repair or replace steam traps | $8,388 | $450 | - |
$8,388
-
MMBtu
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $3,205 | $2,400 | - |
$3,205
-
MMBtu
|
- | |
| 06 | 2.1123: Install automatic stack damper | $1,466 | $1,700 | - |
$1,466
-
MMBtu
|
- | |
| 07 | 2.6214: Shut off pilots in standby equipment | $258 | - | - |
$418
-
MMBtu
|
$(-160.0) | |
| 08 | 2.2511: Insulate bare equipment | $183 | $280 |
$75
1,465
kWh
|
$108
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $14,683 | $5,351 |
$1,258
22,274
kWh
|
$13,585
-
MMBtu
|
$(-160.0) | ||
| TOTAL IMPLEMENTED | $9,514 | $821 |
$868
15,240
kWh
|
$8,806
-
MMBtu
|
$(-160.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs