Assessment Year | 2013 |
---|---|
Principal Product | Signs and graphic solutions |
NAICS | 541430: Graphic Design Services |
SIC | 3993: Signs and Advertising Specialties |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
179,100
ft2
|
Annual Production | 10,000,000
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $300,197 | 7,684,850 |
kWh
|
$0.039 |
Electricity Demand | $133,886 | 13,953 |
kW-mo/yr
|
$9.60 |
Natural Gas | $56,170 | 10,369 |
MMBtu
|
$5.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $54,250 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,383 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $26,647 | $7,150 |
$26,647
683,256
kWh
|
- | - | |
02 | 2.7241: Install outside air damper / economizer on hvac unit | $5,649 | $4,550 |
$5,649
144,850
kWh
|
- | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $4,083 | $15,925 |
$2,873
73,647
kWh
|
$1,210
-
kW-mo/yr
|
- | |
04 | 2.7211: Clean and maintain refrigerant condensers and towers | $4,173 | $240 |
$2,741
70,278
kWh
|
$1,432
-
kW-mo/yr
|
- | |
05 | 2.7231: Use radiant heater for spot heating | $6,694 | $16,250 | - | - |
$6,694
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $763 | $5,865 |
$460
11,792
kWh
|
$303
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,264 | $12,032 |
$762
19,527
kWh
|
$502
-
kW-mo/yr
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,210 | $300 |
$1,210
31,034
kWh
|
- | - | |
09 | 2.3212: Optimize plant power factor | $3,767 | $7,526 | - |
$3,767
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $54,250 | $69,838 |
$40,342
1,034,384
kWh
|
$7,214
-
kW-mo/yr
|
$6,694
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,383 | $540 |
$3,951
101,312
kWh
|
$1,432
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs