ITAC Assessment: OK0778
ITAC logo
ITAC Assessment: OK0778
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product MUSHROOMS
NAICS 311991: Perishable Prepared Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 388,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $664,420 12,383,980
kWh
Natural Gas $712,234 74,278
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $193,402 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $193,402

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Consumption Savings
01 4.652: Replace existing equipment with more suitable substitutes $171,482 $47,731 $20,722
357,855
kWh
$146,520
-
MMBtu
$4,240
-
Tgal
02 2.2136: Install / repair insulation on steam lines $4,464 $1,266 - $4,464
-
MMBtu
-
03 2.2135: Repair and eliminate steam leaks $13,933 $525 - $13,933
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,111 $5,417 $3,111
74,460
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $412 - $412
7,674
kWh
- -
TOTAL RECOMMENDED $193,402 $54,939 $24,245
439,989
kWh
$164,917
-
MMBtu
$4,240
-
Tgal
TOTAL IMPLEMENTED $193,402 $54,939 $24,245
439,989
kWh
$164,917
-
MMBtu
$4,240
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs